Wellkin Level 2 New Offices
Client: C Care (Mauritius) Ltd Description: The conversion of 2nd floor Wellkin terrace to new
Client: C Care (Mauritius) Ltd Description: The conversion of 2nd floor Wellkin terrace to new
Client – Japan Consulate Description – Fit out of 900m2 at 1 Cybercity Location –
Client – Accenture Description – Fit out of 3Nr floors of 5,000m2 overall at 1
Client – Constance La Gaiete Co. LtdDescription – 1,900m2 office building complete with all amenities
Client – Old Jamalacs Tree Co. Ltd Description – A ground plus 2 offices building
Client – Rogers & Co. Ltd Description – Renovation of offices, dining facilities, services installations,
Client – Metropolitan Properties Ltd Description – Office facilities including services installations and external works
Client – Société Aresvi Description – Office complex complete with all amenities and infrastructure –
Client – Coroi Description – Warehouse, stores, offices and amenities – building area 1,500m2 Location
Client – Mauritius Sailor’s Home Society Description – Alteration & renovation comprising of new kitchen,
Unfurnished, within a four to ten storey high concrete framed building, aluminium doors and windows, ceramic floor tiles throughout, complete with concealed electrical wiring, main DB and basic light fittings, plumbing and drainage, white sanitary ware
Rate: – MUR 6,50M
Within a beach resort, comprising 130 to 160 rooms, two restaurants, a spa and gym and external amenities
Rate: – MUR 7,0M – 10,0M/Room
Comprising 110 to 140 rooms, three restaurants, a spa and gym and external amenities
Rate: – MUR 8,0M – 12,0M/Room
Comprising 90 to 120 rooms, four restaurants, a spa gym and hamam, tennis courts and external amenities
Rate: – MUR 12,0M – 18,0M/Room
Within a warehouse configuration
Rate: – MUR 130,000 tonne
6m high at eaves, overall 5,000m2
Rate: – MUR 20,000 – 25,000 /m2
Rate: – MUR 650/m2
Complete with hardwood structures, thatch, fire retardant and bird netting
Rate: – MUR 12,000/m2
Disclaimer for above: All prices are exclusive of 15% VAT.
The above information is given only on an indicative basis and should in no way be utilised to formulate business plans, estimates or otherwise be an aid to decision making towards a construction project. Cost Base date February 2020/2021
The company accepts no responsibility for any misuse that may result from the wrong interpretation of the data.